Steelwork Sentence Examples
The steelwork for a building of any considerable size is almost invariably rolled to order.
A twin legged lanyard is used for climbing steelwork, racking or scaffolding therefore moving between anchor points and still maintaining security.
The Railroad supplied and erected steelwork for an extended canopy.
There are suspended ceilings throughout with areas of exposed painted structural steelwork to the warehouse.
Keith Spencer questioned whether the wall of No 5 was able to support the steelwork.
Painter Brothers supplied tower steelwork Raynesway Construction Services worked on substation civil works.
Algo fabrication We then design the steelwork at our Perth offices in the Algo Business Center.
Once these are both repaired and refitted, it remains to paint the steelwork and then the body can be reunited with the chassis.
Asbestos cladding to the structural steelwork was later revealed.
Immediate remedial work saw all the legs being cut off and new steelwork being welded in place.
AdvertisementThe whole show, including over a ton of secondary steelwork, was installed during a period of three weeks in September 2004.
The external steelwork has been added for the balcony and canopy and a lot of safety equipment is now in place within the frame.
Then, prior to the lift, CAN installed the access ladder, fixed cable trays and removed temporary steelwork.
Above, the concrete tree trunks on the top floor provide fixed base points for setting out the roof steelwork.
The design and build repair program included inspection of the deck steelwork in addition to waterproofing and resurfacing the roadway.
AdvertisementAs events transpired, the Steelwork had to be constructed by means of onsite welding.
Meanwhile, the steelwork for the new health building is at last making an impact on the skyline by the station.
They provide boat repair facilities, doing steelwork repairs but not major replating.
The steelwork design led to awards for its efficiency but sadly toward the end of the century the cladding was failing.
It also gives information on CDM regulations, Investors in People and a register of qualified steelwork contractors.
AdvertisementSteelwork fabrication is up to date and erection is due in the new year.
It is recognized as one of Europes leading constructional steel fabricators, having been involved in the steelwork industry for fifty years.
After erection the steelwork should receive one or two coats of paint; two coats are to be recommended, in which case they should be of different colours.
In German specifications it is required that the steelwork should first receive a coat of boiled linseed oil, in order that the red lead coating should be more coherent with the steel.
Steelwork that has to come in contact with brickwork or concrete should not be painted, but should receive a wash of cement as the brickwork or concrete-work proceeds.
AdvertisementThe steelwork which is exposed to the weather should be painted about every three years, but when it is under cover an interval of five years may elapse.